Deck
An example of the major process of installation is shown below.
  1. Marking joist position
-Mark the steel post (short pillar)position.
-Fix steel post (short pillar) by concrete screw or hole in anchor.
-Install girder onto steel post. 
-Consider girder pitch and set up joist. 
-Maximum joist pitch is 500mm 
(smaller pitch than 450mm is recommended).
  2. Steel post installation
-Fix steel post by concrete screw or hole in anch.
  3. Girder installation
-Joist pitch shall be smaller than 500mm.
  4. Joist installation
-Joist pitch shall be smaller than 500mm.
  5. First deck plate installation
-Prepare a slanting hole on the first installation deck plate and screw the deck onto the joist. 
-From the second plate installation, clip original fastener between deck plate and another plate and screw the fastener. 
-Use #2 Bit of screwdriver.
  6. Cautions for first deck plate installation
-In case screw directly on the deck plate, previously drill a prepared hole on the deck.
-Secure at least 5mm space for both vertical and horizontal joint (Reference: winter time smaller space preferable, summer time larger space preferable).