Deck
An example of the major process of installation is shown below.
1. Marking joist position
-Mark the steel post (short pillar)position.
-Fix steel post (short pillar) by concrete screw or hole in anchor.
-Install girder onto steel post.
-Consider girder pitch and set up joist.
-Maximum joist pitch is 500mm
(smaller pitch than 450mm is recommended).
2. Steel post installation
-Fix steel post by concrete screw or hole in anch.
3. Girder installation
-Joist pitch shall be smaller than 500mm.
4. Joist installation
-Joist pitch shall be smaller than 500mm.
5. First deck plate installation
-Prepare a slanting hole on the first installation deck plate and screw the deck onto the joist.
-From the second plate installation, clip original fastener between deck plate and another plate and screw the fastener.
-Use #2 Bit of screwdriver.
6. Cautions for first deck plate installation
-In case screw directly on the deck plate, previously drill a prepared hole on the deck.
-Secure at least 5mm space for both vertical and horizontal joint (Reference: winter time smaller space preferable, summer time larger space preferable).